Find out
THE DEVELOPMENT STATUS
Check the progress of the Lomas del Higuerón development through the construction progress videos we have prepared for you.
LOMAS 2 PROGRESS
LOMAS 3 PROGRESS
LOMAS 4 PROGRESS
LOMAS 5 PROGRESS

Lomas 5A:
- Landscape planting.
- Pre-sale reviews.
-Water contracting.
Lomas 5B:
- House painting in blocks 4 and 5.
- Kitchen assemblies in block 4 & 5.
- Interior partition walls in blocks 6-7 8-9.
- Installations in all blocks.
-Ceilings in blocks 6-7,8-9,10-11.
- Masonry blocks 10 - 11.
- Installation of roofs in blocks 10 and 11.
- Beginning of swimming pool works.
- Starting of works of urbanization connections.

Lomas 5A:
- Construction of exterior retaining walls.
- Sanitation connections installed.
- Start of plumbing connection adaptation.
- Kitchen assembly.
- Painting of Blocks 1 and 2.
- Construction of attics.
- Completion of exterior flooring.
- Completion of site adaptation for signing CFO.
Lomas 5B:
- Execution of partitioning and painting in Blocks 4 and 5.
- Masonry and partitioning in Blocks 8 and 9.
- Execution of roofs Blocks 8, 9, 10 and 11.
- Installations in B 6-7-8-9.
- Masonry blocks 10 and 11.
- Plastering in Blocks 4 and 5.

Lomas 5A:
- Execution of penthouses.
- Execution of electricity and drainage connections.
- Installation of kitchens.
- Execution of partition walls in Blocks 1 and 2.
- Finishing of roofs in Blocks 1 and 2.
Lomas 5B:
- Execution of partition walls in Blocks 4 and 5.
- Masonry in Blocks 8 and 9.
- Execution of roofing Blocks 4, 5, 8 and 9.
- Structure of Blocks 6, 7, 8 10 and 11.

Lomas 5A:
- Dwellins’ Instalations (water, electricity, air conditioning, sanitation, ventilation, telecommunications).
- Interior partitioning.
- Exterior carpentry.
- Swimming pool.
- Urbanization’s perimetral wall.
Lomas 5B:
- Roof structure finnishing. (Buildings 4-5)
- Starting of Sanitation Works, Air conditioning and ventilation. (Buildings 4-5)
- Masonry. (Buildings 4-5)
- Making the strutures. (Rest of the Buildings)

Lomas 5A:
- Structure of the buildings.
- Inside masonnry of the dwellings.
- Storage rooms in the garages.
- Downpipes drains.
- Plasterboard partitioning.
- Interior installations.
- Roofs.
Lomas 5B:
- Completion of earthworks.
- Micropiles buildings 10 and 11.
- Foundations and structures buildings 6 – 7 – 8 and 9.
- Inside masonery buildings 4 and 5.