Development progress

Find out
THE DEVELOPMENT STATUS

Check the progress of the Lomas del Higuerón development through the construction progress videos we have prepared for you. 

LOMAS 2 PROGRESS

Construction progress
Work in progress 79%
2024
Construction Progress
March 2024
March

- Interior partitioning.
- Exterior drainage.
- Electricity inside the buildings.
- Flooring.
- Painting and plastering of ceilings and walls.
- Interior and exterior servicing and landscaping.
- Roofing.

2024
Construction Progress
January 2024
January

- Interior partitioning.
- Exterior drainage.
- Electricity inside the buildings.
- Flooring.
- Painting and plastering of ceilings and walls.
- Interior and exterior servicing and landscaping.
- Roofing.

2023
Construction Progress
November 2023
November

-Interior partitioning
- Electricity inside the buildings
- Flooring
- Roofing

2023
Construction Progress
September 2023
September

- Installation of interiors.
- Interior urban development works.
- Start of interior carpentries.
- Executing general installations.

2023
Construction Progress
July 2023
July

- Completion of the structure in all the buildings of the development.
- Executing façades in all the blocks.
- Executing roofs in all blocks.
- Executing interior partition walls in all the blocks.
- Executing exterior installations

2023
Construction Progress
May 2023
May

- Executing structure in all blocks of the development.
- Completion of the structure in blocks 1, 2, 3 and 5.
- Carrying out casement enclosure in blocks 1, 2, 3 and 5.
- Installing the metallic structure for the roof of blocks 1, 2, 3 and 5.
- Building the structure in blocks 4, 6, 7 and 8.

2023
Construction Progress
March 2023
March

- Executing concrete structure. - Façades. - Beginning of exterior installations. - Continuing with housing block structures.

LOMAS 3 PROGRESS

Construction progress
Work in progress 90%
2024
Construction Finished
March 2024
March

- Completion of dwellings finishes.
- Installation of kitchens.
- Perimetral sidewalk of the urbanization.
- Terraces, gardens and common areas.

2024
Construction Progress
January 2024
January

- Completion of dwellings finishes.
- Installation of kitchens.
- Perimeter walls of the complex.
- Terraces, gardens and common areas.

2023
Construction Progress
November 2023
November

- Completion of dwellings finishes
- Installation of kitchens
- Perimeter walls of the complex
- Terraces, gardens and common areas

2023
Construction Progress
September 2023
September

- Finishing façades.
- Sanitary installations.
- Interior urban development works.
- Start of interior carpentries.

2023
Construction Progress
July 2023
July

- Finishing plasterboard
- Installation of sanitary ware
- Executing of walls painting
- Implementation of indoor common areas

2023
Construction Progress
May 2023
May

- Exterior cladding.
- Laying flooring on upper terraces.

2023
Construction Progress
March 2023
March

LOMAS 3: Interior partition walls, interior installations, start of interior carpentry ant start of false ceilings. LOMAS 4: Concrete structure and facades.

2023
Construction Progress
January 2023
January

The masonry of the facades of Lomas 3 is being completed and the structure of Lomas 4 is being built.

2022
Construction Progress
November 2022
November

The dwellings that make up the development are being raised and the interior installations are beginning to be installed.

 

2022
Construction Progress
September 2022
September

Work on Lomas 3 and Lomas 4 is progressing well, with the structure of the houses being finalised.

2022
Construction Progress
July 2022
July

We are progressing with the execution of the structure of the first floors of Lomas 3 as well as the pillars and base of Lomas 4.

2022
Construction Progress
May 2022
May

The construction of the Lomas 3 and Lomas 4 housing developments has started and is proceeding according to plan.

LOMAS 4 PROGRESS

Construction progress
Work in progress 90%
2024
Construction Progress
May 2024
May

- Flooring of common areas.
- Finishing of dwellings.
- Work on installations in dwellings and communal areas.
- Conditioning of the community’s perimeter.

2024
Construction Progress
March 2024
March

- Completion of finishes of the dwellings.
- Installation of kitchens.
- Perimeter walls of the urbanization.
- Perimetral sidewalk of the urbanization.
- Terraces, gardens, and common areas.

2024
Construction Progress
January 2024
January

- Wooden carpentry.
- Completion of finishes of the dwellings.
- Installation of kitchens.
- Perimeter walls of the urbanization.
- Terraces, gardens and common areas.

2023
Construction Progress
November 2023
November

- Wooden carpentry
- Completion of finishes of the dwellings
- Installation of kitchens
- Perimeter walls of the urbanization
- Terraces, gardens and common areas

2023
Construction Progress
September 2023
September

- Starting of façades.
- Installation of interiors.
- Interior urban development works.
- Start of interior carpentries.

2023
Construction Progress
July 2023
July

- Finishing plasterboard
- Installation of sanitary ware
- Execution of painting
- Implementation of indoor common areas

2023
Construction Progress
May 2023
May

- Completed enclosure
- Starting with exterior cladding.
- Laying flooring on upper terraces

2023
Construction Progress
March 2023
March

LOMAS 3: Interior partition walls, interior installations, start of interior carpentry ant start of false ceilings. LOMAS 4: Concrete structure and facades.

2023
Construction Progress
January 2023
January

The masonry of the facades of Lomas 3 is being completed and the structure of Lomas 4 is being built.

2022
Construction Progress
November 2022
November

The dwellings that make up the development are being raised and the interior installations are beginning to be installed.

 

2022
Construction Progress
September 2022
September

Work on Lomas 3 and Lomas 4 is progressing well, with the structure of the houses being finalised.

2022
Construction Progress
July 2022
July

We are progressing with the execution of the structure of the first floors of Lomas 3 as well as the pillars and base of Lomas 4.

2022
Construction Progress
May 2022
May

The construction of the Lomas 3 and Lomas 4 housing developments has started and is proceeding according to plan.

LOMAS 5 PROGRESS

Construction progress
Work in progress 29%
2024
Construction Progress
March 2024
March

 Lomas 5A:
- Structure of the buildings.
- Plumbing.
- Electric installations.
- Masonry on dwellings.
- Storage rooms.
- Sanitary sewer downspouts.
- Deck.
Lomas 5B:
- Completion of earthworks.
- Micropyle foundations.
- Structure of buildings 4 & 5.
- Cementation and structure of buildings 6 & 7.

2024
Construction Progress
January 2024
January

 Lomas 5A:
- Structure of the buildings.
- Masonry on dwellings.
- Storage rooms.
- Sanitary sewer downspouts.
Lomas 5B:
- Completion of earthworks.
- Micropyle foundations.
- Cementation and structure of buildings B4 & B5.

2023
Construction Progress
November 2023
November

 Lomas 5A:
- Structure of the buildings
Lomas 5B:
- Completion of earthworks
- Foundations

2023
Construction Progress
September 2023
September

- Start of foundations.
- Start of structures.

2023
Construction Progress
July 2023
July

- Earthworks
- Start of the building’s foundations