Lomas 2

LOMAS 2

Your new home is in LOMAS 2, a modern complex with 160 2 and 3 bedroom homes, located in the natural enclave of Las Lomas del Higuerón (Fuengirola), in the heart of the Costa del Sol.


The project is distributed in 8 buildings of 4 heights, highlighting its spacious penthouses (SKY VILLA), the private gardens on the ground floors (GARDEN VILLA) and the terraces that include all the homes.


All the homes have terraces, two parking spaces and storage room available, as well as spacious communal garden areas, several outdoor swimming pools and a children’s play area.

EXCLUSIVE LOCATION

VIRTUAL MODEL

360 grados

Rotate the model to see LOMAS 2 from any angle

CONSTRUCTION PROGRESS

2024
Construction Progress
March 2024
March

- Interior partitioning.
- Exterior drainage.
- Electricity inside the buildings.
- Flooring.
- Painting and plastering of ceilings and walls.
- Interior and exterior servicing and landscaping.
- Roofing.

2024
Construction Progress
January 2024
January

- Interior partitioning.
- Exterior drainage.
- Electricity inside the buildings.
- Flooring.
- Painting and plastering of ceilings and walls.
- Interior and exterior servicing and landscaping.
- Roofing.

2023
Construction Progress
November 2023
November

-Interior partitioning
- Electricity inside the buildings
- Flooring
- Roofing

2023
Construction Progress
September 2023
September

- Finishing facades.
- Finishing the roof structure.
- The roof of the upper block is already being finished.
- Executing general installations.


2023
Construction Progress
July 2023
July

- Completion of the structure in all the buildings of the development.
- Executing façades in all the blocks.
- Executing roofs in all blocks.
- Executing interior partition walls in all the blocks.
- Executing exterior installations.

2023
Construction Progress
May 2023
May

- Executing structure in all blocks of the development.
- Completion of the structure in blocks 1, 2, 3 and 5.
- Carrying out casement enclosure in blocks 1, 2, 3 and 5.
- Installing the metallic structure for the roof of blocks 1, 2, 3 and 5.
- Building the structure in blocks 4, 6, 7 and 8.

2023
Construction Progress
March 2023
March

- Executing concrete structure. - Façades. - Beginning of exterior installations. - Continuing with housing block structures.

REQUEST FOR INFORMATION

Your new home is waiting for you. Fill in the form and our sales team will contact you to provide you with all the information about the LOMAS 2 and give you personalised advice on the search and purchase of your home.

Ready for your new home?

Responsible: GRUPO TOP GESTIÓN.
Purpose: Resolution of queries, provision of the information required by the interested parties and contact with them, at their request.
Legitimation: Consent of the interested party.
Recipients: No data will be transferred to third parties, unless legally obliged to do so.
Rights: Access, rectify, limit and delete data, as well as file a complaint with the national supervisory authority, as explained in the additional information.
Additional Information: You can consult additional and detailed information on Data Protection in our “Privacy Policy“.