Lomas 3

LOMAS 3

Located in the northern area of the Torreblanca del Sol Development, in the municipality of Fuengirola, we find the LOMAS 3 of Las Lomas del Higuerón.

An open block multi-family building with a total of 30 dwellings consisting of 2, 3 and 4 bedrooms with an average floor area of 104 m2.

The ground floor flats will also have private gardens and the top floor apartments consist of duplexes with a rooftop solarium.

This privileged complex offers wonderful communal garden areas, an outdoor swimming pool and a play area for children.

EXCLUSIVE LOCATION

VIRTUAL MODEL

360 grados

Rotate the model to see LOMAS 3 from any angle

IMAGE GALLERY

CONSTRUCTION PROGRESS

2024
Construction Progress
January 2024
January

- Completion of dwellings finishes.
- Installation of kitchens.
- Perimeter walls of the complex.
- Terraces, gardens and common areas.

2023
Construction Progress
November 2023
November

- Completion of dwellings finishes
- Installation of kitchens
- Perimeter walls of the complex
- Terraces, gardens and common areas

2023
Construction Progress
September 2023
September

- Finishing imitation wood cladding.
- Fitting glass and metal railings.
- Finishing the spiral stairs to the solarium.
- Finishing air conditioning installations.

2023
Construction Progress
July 2023
July

- Finishing plasterboard.
- Installation of sanitary ware.
- Executing of walls painting.
- Implementation of indoor common areas.

2023
Construction Progress
May 2023
May

- Exterior cladding.
- Laying flooring on upper terraces.

2023
Construction Progress
March 2023
March

LOMAS 3: Interior partition walls, interior installations, start of interior carpentry ant start of false ceilings. LOMAS 4: Concrete structure and facades.

2023
Construction Progress
January 2023
January

The masonry of the facades of Lomas 3 is being completed and the structure of Lomas 4 is being built.

2022
Construction Progress
November 2022
November

The dwellings that make up the development are being raised and the interior installations are beginning to be installed.

 

2022
Construction Progress
September 2022
September

Work on Lomas 3 and Lomas 4 is progressing well, with the structure of the houses being finalised.

2022
Construction Progress
July 2022
July

We are progressing with the execution of the structure of the first floors of Lomas 3 as well as the pillars and base of Lomas 4.

2022
Construction Progress
May 2022
May

The construction of the Lomas 3 and Lomas 4 housing developments has started and is proceeding according to plan.

REQUEST FOR INFORMATION

Your new home is waiting for you. Fill in the form and our sales team will contact you to provide you with all the information about the LOMAS 3 and give you personalised advice on the search and purchase of your home.

Ready for your new home?

Responsible: GRUPO TOP GESTIÓN.
Purpose: Resolution of queries, provision of the information required by the interested parties and contact with them, at their request.
Legitimation: Consent of the interested party.
Recipients: No data will be transferred to third parties, unless legally obliged to do so.
Rights: Access, rectify, limit and delete data, as well as file a complaint with the national supervisory authority, as explained in the additional information.
Additional Information: You can consult additional and detailed information on Data Protection in our “Privacy Policy“.